Elitz 2

Studio–3 bedroom apartments · 801 residences by Danube Properties in Jumeirah Village Circle (JVC).

Sold out on Danube's website

Checked 19 Jul 2026

Buyer summary

What we found

The important answers first. Information not yet available is turned into a clear question to confirm.

Developer statusSold out

Sold out on Danube's website.

Construction shown28%

Danube Properties update dated 30 Jun 2026.

Expected handoverOctober 2026

The developer's stated date may change.

Current priceWe could not verify it

We could not verify a current selling price from the pages checked.

Full payment planNot available

The developer says “Pay 1% Monthly”, but we could not verify every payment and date.

Recent salesNot available

We do not yet have reliable project sales data.

Unit typesStudio–3 bedroom apartments · 801 residences

Shown on the project information checked.

Easy to share

Questions you can send.

Use these with the developer, agent or adviser. They make it easy to ask for the newest source and keep the conversation clear.

01

Could you please share the current official selling price, including the unit, currency and date?

02

Could you please share the complete dated payment schedule, including fees and the remaining balance?

03

Could you please share the newest official construction update and inspection date for this exact project and phase?

Dated updates

Construction history

See how Danube's published progress changed over time. The archive shows what Danube published at that time; it is not a government inspection.

Early works

Mobilization completed; shoring in progress; piling design approved; building permit received; main contractor on board.

Archived copyView archived proof ↗
6.30%

Danube reported 6.30% after an internal inspection dated 31 Aug 2024.

Archived 12 Sept 2024View archived proof ↗
14%

Danube reported 14% after an internal inspection dated 31 Jan 2025.

Archived 8 Feb 2025View archived proof ↗
28%

Danube reported 28% after an internal inspection dated 30 Jun 2026.

Current developer pageView current update ↗
Before you reserve

Common buyer questions

Short answers based on the pages checked.

Is Elitz 2 sold out?

Danube Properties' website showed “Sold out” when we checked on 19 Jul 2026. Resale or assignment units may still be available elsewhere.

What is the reported construction progress for Elitz 2?

Danube Properties' construction page showed 28%, with an inspection date of 30 Jun 2026. This is the developer's update, not a government inspection.

What is the current price of Elitz 2?

We could not verify a current selling price from the pages checked. We do not reuse old listing prices.

What is the Elitz 2 payment plan?

The developer uses the phrase “Pay 1% Monthly”, but we could not verify every payment, date and remaining balance.

When is Elitz 2 expected to complete?

Danube Properties stated October 2026 when we checked on 19 Jul 2026. The date may change.