iOffPlanDubai
Dubai off-plan project updates

See what changed.

Follow dated construction percentages and milestones, then open the current page or archived copy behind every point.

1 checked project4 dated points3 measured percentages3 archived proof links

Latest project updates.

Each point keeps the date, publisher and proof together. A developer percentage remains a developer update; an archive shows what its page displayed at that time.

Latest checked update

Elitz 2

Danube Properties · Jumeirah Village Circle (JVC)

14% → 28%+14 percentage pointsLatest point 30 Jun 2026
Early works

Mobilization completed; shoring in progress; piling design approved; building permit received; main contractor on board.

View archived proof ↗