What should you do first if you miss an off plan payment in Dubai?

Check your signed sale and purchase agreement (SPA) and any later payment addendum. Match the demand to the unit, due date or milestone, and amount in the signed schedule. If your bank shows you already sent the money, give the developer’s accounts team the transfer reference and ask for a statement showing where the payment was applied.

If the developer starts Article 11 proceedings, it reports the alleged breach to DLD. DLD checks it and serves a dated, written notice with a 30-day period to comply. It can serve the notice in person, by registered mail with acknowledgement, by email or by another method it prescribes. Check with DLD which notice it served and the response deadline for your case. Dubai Law No. 19 of 2020, Article 11(a)(1)–(2).

If the demand is tied to construction, ask for the milestone in the SPA and the letter from the DLD-approved project consultant showing that it has been reached. Look up the project separately through DLD’s Project Status Enquiry. Save the result with the project number and the date you checked. If the developer also sends its own progress update, file it separately and label it as the developer’s. DLD lists the public enquiry as immediate, with no fee. For a disputed milestone, use the Dubai construction progress guide to record the inspection date and identify the project phase. DLD guidance on milestone payments · DLD Project Status Enquiry.

What can the developer keep if the notice expires?

When the breach remains unresolved at the end of the notice period, DLD issues the developer a document confirming the procedure it followed and the percentage of project completion under Real Estate Regulatory Agency (RERA) standards. The options below apply once the developer has that document. Use the project’s construction percentage to find the row. Then use the unit price in the SPA to work out the retention cap. Dubai Law No. 19 of 2020, Article 11(a)(3)–(4).

Project completion in DLD’s documentDeveloper’s options under Article 11
Below 60%, with construction started on the site in line with approved designsEnd the agreement, retain up to 25% of the agreed unit price and refund the excess.
60% to 80%End the agreement, retain up to 40% of the agreed unit price and refund the excess.
More than 80%Keep the agreement in force and claim the balance, ask DLD to auction the unit to collect the balance and charge the buyer the sale costs, or end the agreement, retain up to 40% of the agreed unit price and refund the excess.

For any refund owed under those termination options, compare two dates. One is a year after termination. The other, if the unit is resold, is 60 days after resale. The earlier date sets the deadline. Ask for the termination date and the date of any resale in writing if you’re working out when the money is due. Dubai Law No. 19 of 2020, Article 11(a)(4).

How do you check the developer’s calculation?

Hypothetical example. The agreed unit price is AED 1,000,000. You’ve paid AED 500,000 towards it, DLD confirms 70% completion and the developer ends the agreement under Article 11. A deduction at the 40% cap is AED 1,000,000 × 40% = AED 400,000. The excess is AED 500,000 − AED 400,000 = AED 100,000. Dubai Law No. 19 of 2020, Article 11(a)(4)(B).

Ask for the same calculation on your unit, with each figure tied to a document. Use the price in the signed agreement, the amounts actually credited towards it and the completion percentage in DLD’s document. If your total includes registration charges, ask for those lines separately so you can see how much went towards the purchase price. Keep the receipts with your off-plan DLD fee records.

A late charge on your statement needs its own explanation. Ask which clause the developer relies on, what amount it used and how it counted the days. We couldn’t confirm a Dubai-wide late-fee rate. For the developer’s provisional deregistration application, DLD says the warning must claim only money due towards the unit price and excludes fines, registration fees, service fees and administrative fees. DLD Request for Termination of Initial Registration.

If the statement is unclear, ask whether it shows a deduction on termination or the unpaid balance on an agreement still in force. If the developer says it has requested an auction, ask DLD for the case reference and the costs and balance claimed. Dubai Law No. 19 of 2020, Article 11(a)(4)(A).

What if construction hasn’t started or RERA cancelled the project?

Article 11(b) requires a full refund of purchaser payments if work hasn’t started for reasons outside the developer’s control, with no negligence or omission on its part. It also requires a full refund if RERA cancels the project by a final reasoned decision. Both go through the escrow law procedures. Ask DLD for the project’s official status and, if cancelled, the decision or case reference. Dubai Law No. 19 of 2020, Article 11(b) · Dubai Escrow Law, Article 15.

The 2017 text allowed a deduction of up to 30% of payments already made in that no-start situation. The 2020 text replaced that provision and uses project completion for the progress bands, where the 2017 English text referred to unit completion. If you’re dealing with steps taken before the later law came into force, give a UAE property lawyer the dates and documents so they can check the transitional provisions. Dubai Law No. 19 of 2017 · Dubai Law No. 19 of 2020, Article 11(b), (d) and (e).

Ask whether an unfinished or cancelled project falls within the remit of the special tribunal under Decree No. 33 of 2020. The decree excludes projects within the Dubai International Financial Centre. A new delivery date on its own doesn’t tell you whether the project is officially unfinished or cancelled. Check your handover delay records and ask DLD what has been recorded for your project. Dubai Decree No. 33 of 2020, Articles 4 and 6.

Can you ask for more time or sell the unit?

Ask the developer for a written reply before the deadline on your notice. Give it the sum you can cover and the date funds will be available. If you reach a settlement through DLD’s mediation, Article 11 calls for an addendum signed by both sides and attached to the SPA. Ask the addendum to state the new due dates, what happens to any notice already served, and how the developer will apply a partial payment. Dubai Law No. 19 of 2020, Article 11(a)(2)(B).

If you’re considering an assignment or resale, ask DLD and the developer which steps are still open for your unit, including whether the arrears or a pending deregistration affect the transfer. The guide to selling off-plan before completion explains the separate checks to make before agreeing dates with a new buyer. Keep your Oqood registration record with the file.

If you’re paying an overdue instalment, confirm the payment instructions through an established developer contact and compare them with the project’s escrow details. DLD’s Mashrooi project view has an Escrow Account field. Use the exact project number so you can catch a mix-up between phases. Ask accounts to confirm the payment has been credited and clarify the status of the notice. DLD Mashrooi project lookup · Dubai Escrow Law, Articles 7 and 9 · Dubai project escrow guide.

If you're arranging a mortgage for the final developer instalment, ask the bank which release condition still needs to be met before you give the developer a payment date.

If you live abroad and are opening an account to fund future instalments, use the non-resident banking guide for off-plan payments to check the transfer method with your bank and the developer.

What should you send DLD or your lawyer?

Call DLD on 800 4488 with your project and unit number. Ask how to verify the notice and the document that confirms the completion percentage. Keep the signed contract and addenda, the instalment schedule, the ledger and proof of payment in date order. If service is disputed, save the full email, envelope or delivery record. Include the sender and date when you save a screenshot. DLD termination service and contact details.

DLD’s real estate violations service excludes contractual disputes, refund requests and compensation claims. Article 11 preserves recourse to courts or arbitration. Ask a UAE property lawyer to read the SPA’s dispute clause and check the forum and any deadline for your case. If the registration has already been cancelled, ask for the date and the reference for that action too. DLD real estate complaints service · Dubai Law No. 19 of 2020, Article 11(g).

What else do buyers ask about a missed instalment?

Does a developer reminder start the 30 days?

The period in Article 11 runs from the formal notice served by DLD. DLD’s deregistration service also refers to a developer warning. If both arrive, save both, compare the amounts and ask DLD which notice sets your deadline. Dubai Law No. 19 of 2020, Article 11(a)(2) · DLD termination service.

Does a delay to handover change the instalment date?

Check what triggers that line in the signed schedule. For a handover-linked or construction-linked payment, ask the developer for the evidence matching the trigger it cites. For a calendar date, ask which contract term or signed amendment would move it. If the developer and you read it differently, give the documents to DLD or your lawyer while there’s still time to respond. DLD guidance on construction-linked payments.

Can I ask to end the deal myself?

Ask the developer for a written proposal showing the termination date, the amount it would keep, any refund date and who will update the DLD record. DLD’s FAQ says it cannot terminate the developer’s contract at the investor’s request. If no agreement is reached, have a UAE property lawyer read the contract and check the available route. DLD FAQs on investor requests to terminate contracts.

If you’ve received a demand, ask the developer for a copy of the signed payment schedule and a dated statement. Call DLD to verify any formal notice and confirm the response date.