Check off plan construction progress Dubai (5 steps)
Check off-plan construction progress in Dubai with DLD's project lookup. Match inspection dates, escrow details and your instalment clause before paying.
To check off plan construction progress, Dubai buyers can use DLD's Project Status Enquiry or Project Status (Mashrooi) in Dubai REST. As of 17 November 2026, check the matching project's inspection details and escrow account, then compare the payment request with your signed instalment clause. Developer-reported progress is not a DLD inspection.


Keep the payment request open beside the agreement. Match the project first, then the dated progress record and payment recipient.
How do you check off plan construction progress Dubai Land Department has recorded?
Open Dubai Land Department's Project Status Enquiry. Select Proceed Now, then search using the land number, project number or project name. Ask the developer for the registered reference if your paperwork only gives a marketing name.
Use this order before considering an instalment:
- Match the project: compare its registered identity with your agreement, including the building or phase.
- Open inspection details: save the percentage and the inspection date shown, plus today's access date.
- Read the account details: compare the project escrow information with your written payment instructions. If the payment request also includes registration, match the DLD and Oqood charges to your agreement.
- Read the payment clause: identify the due date or construction milestone and its evidence requirement.
- Resolve differences: ask the developer for a written explanation tied to your unit and contract clause.
A search result doesn't decide whether a disputed instalment is legally due. Use the five checks to identify what still needs explaining.
Source · Dubai Land Department, Project Status Enquiry · Checked 17 November 2026.
Where are the inspection and escrow details in Dubai REST?
Open Dubai REST → Services → Project Status (Mashrooi). Search by project name and select the matching development. DLD's illustrated instructions show project status, developer details and Escrow Account Details. They direct you to the arrow beside the percentage on the building image for Inspection Details.
Menus can look different from the guide's older screenshots. Look for the named service rather than relying on a button's position. If a field isn't visible, keep it marked “not shown” and ask DLD for help on 8004488.
Record the inspection date separately from the day you opened the app. A screenshot saved today can contain an older inspection. If photographs or a report are available, save their dates and project references too; don't substitute a developer's drone footage for the inspection record.
Source · Dubai Land Department, Mashrooi illustrated user guide · Checked 17 November 2026. The guide's example projects aren't current progress evidence.
Which fields should you save before paying an instalment?
Use one sheet for each registered project. Keep different phases separate until the developer confirms how your unit maps to the record.
| Field | What to write | Question if it doesn't match |
|---|---|---|
| Project identity | Registered name, project number and land reference available | Does this record cover my building and unit? |
| Developer | Name shown in DLD and legal seller in the agreement | Why do the names differ? |
| Progress | Percentage, inspection date and status exactly as displayed | What newer inspection or clarification is available? |
| Completion estimate | Date shown and the wording around it | How does this relate to my contractual delivery date? |
| Escrow | Bank and project account details actually displayed | Who can confirm any missing or changed field? |
| Instalment | Amount in AED, due event, clause and request date | What document establishes this trigger? |
Don't fill blanks from a similarly named tower. If the legal seller differs from the public developer brand, ask for the relationship in writing. Keep the explanation with the agreement rather than treating the difference as proof of a problem.
Save the original result privately. A copy sent for advice can hide unrelated personal and banking information. Your adviser needs the relevant references and wording, not your whole purchase folder.
Does a construction percentage tell you how much to pay?
Read the sale and purchase agreement payment checklist before comparing figures. Write down whether your instalment follows a calendar date, a construction milestone or another event. Then ask which evidence the agreement requires.
Hypothetical example: your annex says an instalment is due when a named construction stage is certified. The developer sends a dated demand, but the DLD result you saved carries an earlier inspection date. Ask for the certificate named in the annex and an explanation of the dates. The older record alone doesn't settle whether the stage has since been completed.
Construction percentage and the share of the purchase price paid measure different things. Don't assume they should be equal or apply the completion percentage to your outstanding balance to calculate what you owe.
If you dispute a demand, have a property lawyer review the clause and notice requirements promptly. Don't treat this checking routine as permission to miss a payment. Default and termination questions need your contract and the applicable law, not a generic percentage table.
How does escrow release differ from your payment schedule?
DLD's FAQ describes an account-management agreement that identifies construction stages for releasing funds. The developer's project manager requests payment after a milestone; the account trustee's engineer visits the site to verify the stage before disbursement to service providers.
Request the contractual basis for your instalment, even if the developer says a bank has approved a release.
Under Law No. 8 of 2007, Articles 7 and 9, the account is opened in the project's name, and separate projects need separate escrow accounts. Article 12 allows depositors or their representatives access to their own accounting records and copies. It doesn't promise public access to every purchaser's deposits or the project's full bank statement.
Once you've checked why an instalment is due, use the Dubai escrow checklist for buyers to check where it goes. Keep the transfer reference and the receipt that credits it to your unit.
Sources · Dubai Land Department, escrow disbursement FAQ · Dubai Supreme Legislation Committee, Law 8 of 2007 · Checked 17 November 2026; Arabic governs legal interpretation.
If the developer says the account is still being set up, ask which step is outstanding. The Dubai project escrow opening guide shows where the developer, trustee and DLD each come in.
What if the escrow bank details have changed?
Contact the developer using a route you already hold in your signed documents. Ask for written confirmation of the registered project, beneficiary, bank and account details. Compare that reply with the official project record and ask DLD about anything you still can't reconcile.
Keep the original demand and the revised instructions. Write down who confirmed the change, how you reached them and when. A forwarded screenshot by itself doesn't explain why the account changed.
The escrow-account transfer guide explains the developer's transfer process. Don't confuse an account-transfer application with confirmed instructions for your own payment.
After an authorised payment, keep its bank reference and the developer's receipt. Ask the developer or account trustee how to obtain your own accounting record if a payment isn't reflected. Leave the account's balance or operating status as unconfirmed if you haven't obtained evidence of it.
What if DLD and the developer show different progress?
Put the two records side by side. Label each publisher, project, percentage and data date. Ask whether they describe the same scope: a structural frame, one tower and the whole registered project need not be the same measure.
Hypothetical comparison: an email reports “structure complete”, while a project record gives an overall completion percentage. Ask what remains in the overall scope. Don't average the two numbers or turn them into a predicted handover date.
If the official entry appears unchanged, ask DLD whether a later inspection is available. We couldn't confirm a universal inspection-refresh interval. The service card's Immediate turnaround describes the enquiry service, not a promise that the underlying inspection happened today.
If the search finds nothing, follow that up too. Recheck spelling and project or land number, then contact DLD. Record “no matching result obtained”, rather than guessing that the project is unregistered or cancelled.
For a changed delivery programme, use the delayed-handover document steps. Keep the construction question separate from the reason for the delay and any claim you intend to make.
Does 100% completion mean you can move in?
Ask for your unit's handover notice, completion documents, inspection arrangements and outstanding account statement. A percentage doesn't tell you which documents you must sign or when your keys will be available.
Check the Oqood registration record separately. Finding a project in Mashrooi doesn't establish that your individual purchase has been registered.
Before booking movers, get your appointment and any remaining conditions in writing. Take the unit number and contractual specification into the inspection discussion. Another buyer's handover announcement doesn't confirm when your home will be available.
If the final instalment will come from a bank, use the handover mortgage checklist to check which completion documents the bank needs before it will release funds.
Where do you ask about a stalled project or disputed payment?
If the developer says you’ve missed a milestone instalment, check how DLD handles a missed off-plan payment and ask which notice and completion figure it is relying on.
Start with DLD support on 8004488 for a project-record question. Give the project number, result date and the exact field you need explained. DLD's FAQ describes periodic RERA monitoring, but that doesn't give your project a guaranteed completion date.
For a possible regulatory violation, check DLD's real-estate-company complaint service. Its terms exclude contractual termination, refunds, indemnity and rental disputes, and include an intake restriction for contracts concluded more than six months ago. Ask DLD which route fits before relying on that form.
Its published five-business-day service time isn't a promise of payment, compensation or a court decision. For a contractual remedy, take the agreement, payment history, project record and correspondence to a property lawyer. Article 15 of the escrow law addresses incomplete projects, but it doesn't establish a refund date for your purchase.
Source · Dubai Land Department, complaint scope and terms · Checked 17 November 2026.
Buying from an existing off-plan owner? The off-plan resale process and settlement guide adds the seller records, developer consent and remaining-payment checks to your project research.
What else do buyers ask about progress checks?
How much does the DLD project-status enquiry cost?
DLD lists fees as Not Applicable and the expected completion time as Immediate, checked 17 November 2026. Those entries describe the lookup. They don't include a private inspection, legal review or any bank charge associated with your purchase.
Can you use the service without a project number?
The website instructions also allow a project name or land number. DLD's Dubai REST guide uses project-name search. If several results look similar, ask the developer for the registered reference before choosing one.
Can you see whether your own instalment reached escrow?
Project account details alone don't prove receipt of your transfer. Keep the bank confirmation, developer receipt and payment reference. Ask the account trustee about access to your own accounting records under Article 12.
Do you need to check every month?
We couldn't find an official rule on how often to check. As a practical routine, save a dated result when reviewing an instalment or a revised delivery notice. Retain earlier copies so you can ask about changes without relying on memory.
Before your next payment, complete the worksheet above and send one focused question for every blank that matters to that demand.
Sources
- Dubai Land Department — Project Status Enquiry — dubailand.gov.ae · checked
Official service card opened today. Inputs are land number, project number or project name. Website, Dubai REST and WhatsApp channels; support 8004488. Fees and required documents are Not Applicable; published service time is Immediate, not an inspection-refresh promise. No individual project searched or authenticated.
- Dubai Land Department — Project Status (Mashrooi) user guide — dubailand.gov.ae · checked
Official illustrated guide opened today. Services to Mashrooi to project-name search; project, developer and escrow details; arrow beside completion percentage opens Inspection Details. Historical sample screens are not current project evidence. Units are percentage completion and dates as displayed.
- Dubai Supreme Legislation Committee — Law No. 8 of 2007 — dlp.dubai.gov.ae · checked
Official English text opened today. Articles 7 and 9 cover project-named and separate accounts; Article 12 concerns depositors' own accounting records; Article 15 addresses incomplete projects. Issued 6 May 2007. Arabic governs interpretation. No project balance, buyer-specific refund or account validity verified.
- Dubai Land Department — Frequently Asked Questions — dubailand.gov.ae · checked
Official FAQ opened today. Describes construction-stage escrow disbursement, trustee-engineer site checks, periodic RERA progress monitoring and project-status enquiries. No fixed inspection interval or project-specific payment decision confirmed.
- Dubai Land Department — Complaint Against a Real Estate Company — dubailand.gov.ae · checked
Official service card opened today. Real-estate violation reporting requires supporting documents; excludes contractual termination, refunds, indemnity and rental disputes. Intake wording excludes contracts concluded more than six months ago. Published service time five business days; not a court deadline or refund promise.
Next stepDue diligence →
More in Due diligence
Start here: Due diligence
- Anti-trust Law Dubai: Merger Thresholds (2026 Update)
- BUA Meaning in Real Estate: What Built-Up Area Includes
- Buying property in Dubai with crypto: payment checks (2026)
- Dubai green building regulations: Al Safat (Checklist)
- Dubai apartments: a buyer guide to costs and checks 2026
- Sky Palace in Dubai: plans, ownership and costs 2026