By the iOffPlanDubai team.

How do you check a unit size difference at handover?

Put your signed sale and purchase agreement (SPA) beside the final unit plan or survey. Match the project, tower, floor and unit number before comparing areas. Then find the agreed net area in the SPA and the attached plan. Article 13 uses that figure as the starting point for measuring a shortage or excess. Executive Council Resolution No. 6 of 2010, Article 13(5).

Look at the label on each figure. A brochure may say built-up area (BUA), the sales sheet may give a total with a balcony, and a room sketch may show dimensions taken between finished walls. Write down the labels as they appear. If they differ, ask the developer to show how each figure was built up. The Dubai BUA and floor-plan guide explains why a price-per-square-foot comparison needs the same type of area on both sides. In two Lamtara 1 one-bedroom plans, outdoor space accounts for 272 of the 273 sq ft difference between the totals.

Put these documents side by sideWhat to mark
Signed SPA and plan, including signed amendmentsNet area, unit ID, plan revision and variance clause.
Final survey or approved unit planUnit ID, final net area, measurement date, drawing revision and what was counted.
Oqood record or title deed and the DLD map if availableUnit ID and any area shown. Ask which registered figure is current.
Handover pack or final demandAny area adjustment, the calculation used and the wording of any acceptance or release.

If the SPA and its own attached plan disagree, ask for both to be reconciled before choosing a baseline. Keep earlier marketing plans too, especially if the layout changed, and label them by date. For the provisional record, see the Oqood registration guide. Executive Council Resolution No. 6 of 2010, Article 13.

How does the 5% rule work when the unit is smaller?

Article 12 of Dubai Law No. 13 of 2008 calls for compensation for a decrease unless it’s inconsequential. Article 13 of the implementing resolution sets the more-than-5% test. Subtract the measured net area from the agreed net area. Divide the difference by the agreed net area, then multiply by 100. Dubai Land Department (DLD) uses square metres. If one document uses square feet, DLD’s conversion is sq ft ÷ 10.7639104 = m². Keep the full figures until you’ve calculated the percentage. Dubai Law No. 13 of 2008, Article 12 · Executive Council Resolution No. 6 of 2010, Article 13 · DLD FAQs on area changes and units.

Hypothetical example. The signed plan specifies 100 m² net area. A final survey on the same basis shows 93 m². The shortage is 7 m² and the percentage is 7 ÷ 100 × 100 = 7%. A comparable survey of 95 m² would give exactly 5%. Article 13 says more than 5%, so the 95 m² result doesn’t cross that threshold. Executive Council Resolution No. 6 of 2010, Article 13(3)–(5).

The resolution says the agreed unit price is the basis for compensation. If the developer sends an offer, ask which area it used, what value per square metre it applied and how many square metres it included in the adjustment. For the example above, have it show how it treated the full 7 m² shortage and the 2 m² beyond the 5% threshold. We couldn’t confirm a single payout formula for every SPA from the official text and guidance. Ask a UAE property lawyer to check the calculation if the basis is disputed. Executive Council Resolution No. 6 of 2010, Article 13(4) · DLD FAQs on area changes.

Can the developer charge you for extra space?

Article 12 of Law No. 13 of 2008 addresses increases after delivery and says the developer cannot claim an increase in the price for that extra area. Article 13(2) of the implementing resolution says excess net area is disregarded unless agreed otherwise. DLD’s FAQ says a charge for excess area needs an express agreement in the sale contract. If there’s a bill at handover, ask for the signed clause, survey and date the extra area was established. A UAE property lawyer can read the timing and clause against both provisions. Dubai Law No. 13 of 2008, Article 12 · Executive Council Resolution No. 6 of 2010, Article 13(2) · DLD FAQs.

Check both directions in the variance clause. Note the threshold for a smaller unit, any separate threshold for a larger one and the written calculation in each case. Check how it defines the area and who measures it. If a bill includes a terrace, parking space or storage room, ask where that space is shown and whether its area is counted in the net figure or recorded separately. Dubai Law No. 6 of 2019, Article 9.

Who can measure the unit and correct the DLD record?

Ask the developer’s handover team for the final survey or approved unit plan, with the date and area schedule. If the email gives just a number, ask the team to point to it on the drawing. If you can get access, an independent survey can help identify the disputed boundary. Ask the surveyor to use the same basis as the approved plan and identify any exclusions in the report. Confirm with DLD what evidence its Survey Department can accept before commissioning work. DLD project details amendment service.

A tape measure can help you spot where the numbers differ. Take a dated photo and mark the room or balcony on the plan. Ask a handover snagging inspector what their brief covers. A list of defects can record what you saw. For the area question, ask for a separate measurement schedule showing where the measurements start and end.

If the final invoice has arrived as well, follow the certificate and final payment checks alongside your request for the final survey.

If the developer agrees the registered details are wrong, ask who will file the correction and when you can see it. DLD’s project-details service allows the developer to amend unit area. The developer appoints a survey company, which prepares data against approved plans and sends the application to DLD’s Survey Department for review. Ask for the application reference and the revised map or record when DLD has dealt with it. DLD project details amendment service.

If the bank's valuer used the old area, ask the lender whether it will review the figure against the final survey. The low bank valuation guide shows what to send with that request.

What does a DLD survey or unit map cost?

DLD’s Real estate survey application starts with an owner’s application and requires access for a site visit. DLD takes measurements and issues a survey report. The service lists AED 600 to survey a unit or villa, plus AED 10 knowledge fee and AED 10 innovation fee, which adds up to AED 620. The expected service time is three business days. If you’re still on Oqood, ask DLD who can apply and how to arrange access before you book.

DLD’s Property Map Request service is for owners of registered property. Its published fee for an apartment or villa map is AED 250, plus AED 10 knowledge fee and AED 10 innovation fee per drawing. That’s AED 270 for one drawing at those listed rates. DLD gives an expected service time of 12 minutes and lists Dubai REST, its website and trustee centres among the channels. Ask for the map if you need the registered drawing and the survey if you need a site measurement. DLD Property Map Request.

If you can’t access a map yet, call DLD on 800 4488 with the unit and project number. Ask what’s available at your registration stage and which plan the developer can provide. If the title deed and final plan differ, ask which figure is on the current register and whether there’s a correction already in progress. DLD Property Map Request and support · DLD project details amendment service.

What should you put in writing before taking the keys?

Send the developer the two figures and their document names in one email. Size is one of seven checks in our handover notice checklist. Attach the relevant SPA page and plan, and mark the exact part of the unit you want checked. You can write, “The signed unit plan shows 100 m² net. The final plan you sent shows 93 m². Please confirm both were measured on the same basis and show how you applied Article 13 and the SPA variance clause.” Use your own figures and ask for the reply before the date printed on the handover notice. Executive Council Resolution No. 6 of 2010, Article 13.

If the form mentions full acceptance, waiver or settlement, ask for a copy in advance and have a UAE property lawyer check it before you sign. Ask the developer whether it will record the open issue in writing and what happens to the handover appointment or final instalment while it reviews the difference. If the due date is close, check the Dubai missed off-plan payment procedure alongside the SPA.

Ask DLD whether it can help the parties reach an agreed adjustment. Article 14 allows DLD to attempt conciliation. If the parties reach an agreement through that process, it is signed and approved by DLD. Executive Council Resolution No. 6 of 2010, Article 14.

For a suspected regulatory violation, DLD lists a Real Estate Company complaint service. Its published terms exclude contractual disputes and claims for compensation or refund. Ask DLD about the record or survey, and ask your lawyer which forum can hear a disputed payment or contractual claim. Keep the developer’s reply and any DLD reference with the plan revisions. DLD real estate complaints service.

What else should you check when a unit changes size?

What if only the balcony or one room is smaller?

Ask for the size of that part on both plan versions and for the total net area on the same basis. Article 13 compares the unit’s net area. If the total is unchanged but the layout differs, ask the developer which revision it built. Give a lawyer the layout or specifications clause if that change is in dispute. Executive Council Resolution No. 6 of 2010, Article 13 · Dubai Law No. 6 of 2019, Article 9.

Does the registered area affect service charges?

For jointly owned property covered by Law No. 6 of 2019, the owner’s share uses the unit area recorded in the Real Property Register. Ask the management company which area it used on the invoice and what it needs if DLD corrects that figure. The Mollak service charge guide shows what to compare on the bill. Dubai Law No. 6 of 2019, Article 25.

Can you raise the difference after handover?

Write to the developer when you spot the discrepancy. The UAE Civil Transactions Law in force since 1 June 2026 sets a one-year period from delivery for the sale claims described in Articles 475–476, including a price reduction claim. Give a UAE property lawyer the notice and signed handover papers. Ask which law and deadline apply to your claim and which date counts as delivery. UAE Civil Transactions Law, Articles 475–477.

Can you ask to end the sale because of the change?

Article 20 of Dubai’s implementing resolution lists a material departure from agreed specifications as a ground on which a buyer can ask the competent court to end the contract. Ask a UAE property lawyer to compare the signed specifications and final survey before deciding which remedy to pursue. Executive Council Resolution No. 6 of 2010, Article 20.

Start by asking for the dated final drawing and its net area. Mark the figure on the signed plan while you wait for the reply.